Regulation

The Construction (Design and Management) Regulations 2015 (SI 2015/51)

The Construction (Design and Management) Regulations 2015 (SI 2015/51), issued by UK Government (statutory instrument). 3 free templates written against it, with the provisions cited and a link to the publisher.

Issued by
UK Government (statutory instrument)
Applies in
GB - Great Britain (England, Wales and Scotland) unless the provision states otherwise

Read it at the publisher

Provisions our templates cite

Each provision below was found by our automatic check on the publisher's own page and approved by a person for the template that cites it. The wording is the publisher's, not ours.

  1. reg. 12(1)
    During the pre-construction phase, and before setting up a construction site, the principal contractor must draw up a construction phase plan, or make arrangements for a construction phase plan to be drawn up.
    Read it at the publisher
  2. reg. 13(4)
    The principal contractor must ensure that— (a) a suitable site induction is provided; (b) the necessary steps are taken to prevent access by unauthorised persons to the construction site
    Read it at the publisher
  3. reg. 15(2)
    A contractor must plan, manage and monitor construction work carried out either by the contractor or by workers under the contractor's control, to ensure that, so far as is reasonably practicable, it is carried out without risks to health and safety.
    Read it at the publisher
  4. reg. 15(7)
    A contractor must not employ or appoint a person to work on a construction site unless that person has, or is in the process of obtaining, the necessary skills, knowledge, training and experience to carry out the tasks allocated to that person
    Read it at the publisher
  5. reg. 22(1)
    All practicable steps must be taken to prevent danger to any person, including, where necessary, the provision of supports or battering, to ensure that— (a) no excavation or part of an excavation collapses
    Read it at the publisher
  6. reg. 30(1)
    suitable and sufficient arrangements for dealing with any foreseeable emergency must be made and, where necessary, implemented, and those arrangements must include procedures for any necessary evacuation of the site or any part of it.
    Read it at the publisher
  7. Sch. 2 para. 1(1)
    Suitable and sufficient sanitary conveniences must be provided or made available at readily accessible places.
    Read it at the publisher

Templates that cite it

Generate a free template for CDM 2015

Or upload a photo of the job and see its hazards, with the UK regulation behind each. Check risks from a photo